VCICDP Road Development Project
The Visakhapatnam-Chennai Industrial Corridor Development Program (VCICDP) includes the construction and widening of the road from Neleballi to Routhusuramala and the development of a two-lane road from Srikalahasthi–Yerpedu to Pallamala (APRDC/05), covering Km 0+000 to Km 9+207 in Thottambedu and B.N. Kandriga Mandals, Chittoor District. As part of the reporting process, an inception report has been prepared, highlighting the accomplishments of the preparatory phase and outlining the work plan for the project period.
Key preparatory activities have been completed on schedule. Additionally, the Asian Development Bank (ADB) team, along with Roads & Buildings (R&B) officials, conducted a field visit to Thimmaji Kandriga–Naidupeta Road (APRDC-04) and met with the Revenue Divisional Officer (RDO) at Sullurupeta to discuss project progress and coordination.